Completed Arena
(Click on a small picture to go to the album)
September 2, 2008 August 4, 2008 July 18, 2008 July 14, 2008 July 08, 2008 July 07, 2008 July 01, 2008 June 24, 2008 June 12, 2008 June 11, 2008 May 28, 2008 May 21, 2008 May 19, 2008 May 15, 2008 April 24, 2008 April 23, 2008 April 21, 2008 April 19, 2008 April 17, 2008 April 16, 2008 April 15, 2008
Concrete in stall barn aisle is complete. Stalls are underway. The electric main panel has been installed. The main water hydrant has been installed. We have laid down tubing for radiant heating in the feed, tack, and show tack rooms. All interior vmatch has been installed in the indoor. All siding on the stall barn has been installed along with the exterior stall doors. Each of the six exterior stalls will have their own paddock directly attached to the stall.
(Click on a small picture to go to the album)
Roof on the stall barn is complete along with the ceiling. All lights, fans, and speakers have been installed in the arena. Kick-boards and V-match installation in the arena is well underway.
(Click on a small picture to go to the album)
Posts are in for the stall barn. Still more fill has been brought in. Kickboards on the northend have started being installed.
(Click on a small picture to go to the album)
The foundation for the stall barn is complete. The west side and south side siding is complete besides the trim. The siding on the north side is in the works. Installation of lights has started.
(Click on a small picture to go to the album)
Footings for the stall barn went in. Windows on the west end were installed along with some siding.
(Click on a small picture to go to the album)
Ceiling is in.
(Click on a small picture to go to the album)
The metal roof is complete.
(Click on a small picture to go to the album)
Everything is now ready for the metal roof to go up.
(Click on a small picture to go to the album)
Today the crane put the trusses up.
(Click on a small picture to go to the album)
The trusses are complete. The site for the stall barn has been filled and is ready for the footings.
(Click on a small picture to go to the album)
The trusses are tied together in to 36' wide sections on the ground.
(Click on a small picture to go to the album)
Trusses were delivered today. The north side wall frame is nearly complete. Fill for the stall barn is being layed down.
(Click on a small picture to go to the album)
Today most of the posts were installed.
(Click on a small picture to go to the album)
The foundation for the arena is complete They have started adding the foundation drains and are back filling.
(Click on a small picture to go to the album)
Forms came off the west side foundation while more concrete was pour on the south wall foundation and footings.
(Click on a small picture to go to the album)
Forms for the west side foundation went up and concrete was poured.
(Click on a small picture to go to the album)
Concrete was poured for the west side footings.
(Click on a small picture to go to the album)
Forms for the west side footings went in today.
(Click on a small picture to go to the album)
More fill and trenches for the west side footings.
(Click on a small picture to go to the album)
More fill today.
(Click on a small picture to go to the album)
Fill was brought in today. To level the site, the west end is cut down and the east end is being built up with fill.
(Click on a small picture to go to the album)

This site is designed and maintained by
Janet Long. Copyright ©2000-2011 Northeast Shires. All rights reserved.
No portion of this site may be reproduced or copied without the express written
consent of Northeast Shires.